Custom Highett: Project Updates – Roof Trusses, Scaffold and Internal Works
Construction at Custom Highett has been progressing well and we are excited to report that the residences are well and truly starting to take shape!
NEWS
Construction at Custom Highett has been progressing well and we are excited to report that the residences are well and truly starting to take shape!
With two new sites acquired in the highly sought-after suburbs of Brunswick and Essendon, Young Group are proud to announce plans for two new projects.
Young Group’s latest project Tomorrow, is ideally placed to enjoy the very best of Northcote – which was reported as Victoria’s most liveable suburb in the recent ‘Future Victoria’ report by accounting firm PwC.
Custom continues to take shape as the form rises to Level 3.
We are excited to share that the Young Group – Collins Street office, has been shortlisted for both the Australian Interior Design Awards and the IDEA Awards, celebrating the category of ‘workplace design’.
With excavation, footings and civil works all complete – construction is moving along nicely at Custom Highett.
We are pleased to introduce our latest project ‘Tomorrow Northcote’.
27 residences, combining sustainable living and forward thinking design, that will grow with you into the future.
It is our great honour to announce that our highly anticipated project Custom Highett is now sold out and construction is progressing well on site.
We are pleased to share that the construction is well underway, with demolition completed and excavation to follow.
We are proud to partner with Balmain & Co to bring Custom Highett to life.
With basement construction and the ground floor structure both complete, we anticipate to have level 1 concrete poured in early September.
We are pleased to announce that Tomorrow Northcote has progressed well since our last update.
Basement two is now complete and the basement one formwork will be finished by the end of the week, with concrete pouring to follow.
We are pleased to announce that construction is progressing well at Tomorrow Northcote.
Basement excavation work is now fully completed, shotcrete to basement is almost finished, and we are not far from seeing the crane up on site.
With basement construction and the ground floor structure both complete, we anticipate to have level 1 concrete poured in early September.
We are pleased to announce that Tomorrow Northcote has progressed well since our last update.
Basement two is now complete and the basement one formwork will be finished by the end of the week, with concrete pouring to follow.
We are pleased to announce that construction is progressing well at Tomorrow Northcote.
Basement excavation work is now fully completed, shotcrete to basement is almost finished, and we are not far from seeing the crane up on site.